Crane Creek / M-1 Canal flow restoration project
Updated on 4-22-2024
The M-1 Canal is a 100-year-old, man-made flood control feature in Brevard County that cuts through the historic drainage divide between the St. Johns River and the Indian River Lagoon.
The M-1 Canal diverts stormwater flow from 5,300 acres of drainage area in Melbourne, West Melbourne, Melbourne Village and portions of unincorporated Brevard County and sends the water east to the Indian River Lagoon via Crane Creek. Nutrients within runoff from this currently diverted watershed degrade water quality in the Indian River Lagoon and provide fuel for algal blooms.
The Crane Creek / M-1 Canal Project — identified in the 2017 Indian River Lagoon Stormwater Capture and Treatment Feasibility Analysis and led by the St. Johns River Water Management District — will substantially reduce nutrient loading to the Indian River Lagoon. Construction of the project will result in restoring the baseflow in the M-1 Canal westward for treatment in a constructed stormwater treatment area prior to discharging to the St. Johns River Basin.
Project components include an operable weir east of Evans Road, two pump stations, two pipeline force mains and a stormwater treatment area west of Interstate 95. The operable weir – which allows capture of runoff for the east pump station – is engineered to have no impact on the existing flood control capability of the M-1 Canal.
This project reduces nutrient loadings to the Indian River Lagoon while also providing an alternative water supply source to downstream users by restoring 7 million gallons of freshwater flow per day to the St. Johns River.
Nutrient load reduction estimates to the Indian River Lagoon are:
- Total nitrogen 24,000 lb./yr.
- Total phosphorus 3,100 lb./yr.
Project schedule
July 2017
- Engineering design start
FY 2018
- Hydraulic and hydrologic modeling
- Engineering design
- Land acquisition
FY 2019–2022
- Completion of land acquisition
- Engineering design
- Permitting
FY 2023–2025
- Construction
Project milestones
- Hydraulic and hydrologic modeling is completed
- Design is completed
- Governing Board approved execution of construction contract (January 2023)
- Construction has begun
Project partners
- Brevard County ($2.03 million funding contribution)
- Florida Department of Environmental Protection ($2.45 million funding contribution)
- Federal sources administered through Florida Department of Environmental Protection ($4.5 million funding contribution)
- St. Johns River Water Management District (approx. $14–15 million)
- Contact: cranecreekproject@sjrwmd.com
FAQs
When is the project slated to begin and when will it be completed?
The construction phase of this project is scheduled to begin in spring 2023. The anticipated completion date is April 2025.
Reversing some of the flow in M-1 Canal and sending stormwater west to the St. Johns River will help the Indian River Lagoon, but how will the stormwater be cleaned before it reaches the St. Johns River?
Water from the M-1 Canal will be pumped under Interstate 95 and Heritage Parkway to a stormwater treatment area (STA). The STA provides treatment for the water which is then pumped into a pipeline that will be constructed along the Heritage Parkway and the U.S. Highway 192 corridor. The pipeline will discharge to District-owned marsh land adjacent to the St. Johns River, and ultimately the St. Johns River.
Will construction impact local traffic, especially in nearby neighborhoods?
Construction of this project will have no impact on local traffic.
Will the installation of the weir at the M-1 Canal contribute to flooding in nearby neighborhoods already prone to flooding during storm events?
This project will have no adverse impact on the existing stormwater system. Flood protection is a priority and has been carefully analyzed and modeled. The system is designed so that the proposed weir can be lowered (open position) in the event of a major oncoming rainfall event (such as a hurricane or tropical storm). Redundant automatic sensors in the canal will also lower the weirs if the water in the canal reaches certain elevations. The system is continually monitored by operations staff to ensure it is functioning properly. Additional analysis has been performed to ensure that even if the weir is left in the up position, flood protections will remain unchanged. This is possible because the M-1 Canal will be widened over the weir to maintain current flow capacity.
Does the additional water benefit the river?
The additional water will benefit the St. Johns River by restoring historic baseflow from the watershed that was diverted from the St. Johns River to the Indian River Lagoon.
Who do I call or email if I have additional questions?
If you have questions about this project, please email cranecreekproject@sjrwmd.com or call Marc Van Heden at 321-676-6604.